Viewing Actual Hours

The Display menu contains an option that allows users to show or hide the resource’s “Actual Work” information in the Resource Plan. Activating this option adds a column to Resource Plan that displays the total amount of actual work performed by each resource for the given resource type and time period on the task schedule.

To view or hide the actual hours worked by your resources:

  1. Open the Display menu in the lower-left corner of the Resource Plan.
  2. Click on the Actual option.

When the Actual option is selected, a new column displays within each time period in the Resource Plan. This column displays the total actual work, either Hours or FTEs, for each resource within the WBS task schedule.